File #: CON. NO. 131-2018    Version: 1 Name: East Gate WM Replacement Phase 1
Type: Contract Status: Consent Agenda
File created: 8/30/2018 In control: Utilities
On agenda: 9/11/2018 Final action: 9/11/2018
Title: Approval of Contract With Andrew Site Work, LLC in The Amount of $1,017,286.64 for East Gate Water Main Replacement, Phase 1
Attachments: 1. Memorandum, 2. Solicitation Documents, 3. Bid Submittal - Andrew Sitework

Title

Approval of Contract With Andrew Site Work, LLC in The Amount of $1,017,286.64 for East Gate Water Main Replacement, Phase 1